SCHTÖBÄRÄ – ENTDECKÄ – GWUNDRIG BLIIBÄ

a CURIOUS COMMUNITY

Façade elements, commercial building

October 6, 2026

Sawtooth roof structure

August 27, 2026

Residential building façade

August 27, 2026

Drone footage

July 16, 2026

Concrete base elements

July 7, 2026

Reinforcing the floor slab

June 1, 2026

Utility lines

May 1, 2026

Backfilling and scaffolding

April 16, 2026

Site overview

March 11, 2026

Main construction and earthworks

February 9, 2026

Snow and sub-zero temperatures

January 5, 2026

View from above

December 18, 2025

Tower crane

December 4, 2025

The first snow

November 24, 2025

Earthworks around the piles

November 10, 2025

Piling work

October 7, 2025

Excavated material

September 29, 2025

The excavator arrives

August 27, 2025

Groundbreaking

August 25, 2025

Load more

Live stream

Follow the development of the STEINEL site up close – around the clock and in real time. Our live camera broadcasts directly from the construction site and shows the progress of the current construction phase, from the first excavation work to the completion of the buildings. As a resident, tenant or interested party, you always stay informed about the status of the work and can follow the creation of the new neighborhood step by step.

View live image

Current status – questions & answers

Icon

How far has construction progressed?

The development of the site is progressing in stages. In the first realization phase, the new commercial building A and the new residential building D are being built. Construction is on schedule and progress is documented continuously. As soon as individual parts of the buildings are completed, this will be communicated here.

Icon

When is construction scheduled to be completed?

The project is being implemented in several phases. The first construction phase – consisting of commercial building A and residential building D – is currently under way. Completion of the construction work is planned for autumn 2027. Move-in dates will be published as soon as they are confirmed.

Icon

Which companies are involved in the project?

Steinel Immobilien AG works with companies and specialized partners – including experienced architectural firms, specialist planners and local trades. This close collaboration ensures high construction quality and the sustainable development of the entire site.

General planner
Batimo AG Architekten SIA 4802 Zofingen


Utility planner
Gasser + Partner AG 6460 Altdorf
Structural engineer
Suisseplan Ingenieure AG 6003 Luzern

Electrical engineer

Wolf Plan AG 8330 Pfäffikon ZH

HVAC and plumbing engineer

Planea AG 5612 Villmergen

Fire protection engineer, building plot A

BDS Security Design AG 3006 Bern

Timber construction and fire protection engineer, building plot D

Pirmin Jung Schweiz AG 6210 Sursee

Landscape architect

Freiraumplanung Wolf 13156 Berlin

Geology and contaminated sites

Jäckli Geologie AG 6330 Cham

Traffic planner

TEAMverkehr.zug ag 6330 Cham

Building physics and acoustics

Grolimund + Partner AG 5000 Aarau


Piling
Marti Gründungstechnik AG 3302 Moosseedorf
Earthworks
Föllmi AG Bauunternehmung 8835 Feusisberg
Main construction works
Bolfing AG 6431 Schwyz

Plumbing

Alfons Iten AG 8840 Einsiedeln

Lifts

Schindler Aufzüge AG 6030 Ebikon

Ventilation systems

Annen + Schibig AG 6438 Ibach

Transformer station

Cellpack Power Systems AG 5612 Villmergen

Façade scaffolding
Schuler Gerüst GmbH 6423 Seewen

Prefabricated timber construction
Kälin HolzTechnik AG 8840 Trachslau

Prefabricated steel construction
H. Wetter AG Hallen Stahl- + Metallbau 5608 Stetten

Heating systems
Hans Ziegler AG 8853 Lachen

Façade construction

Schmid Bauunternehmung AG 6030 Ebikon

Wood-metal windows

Ego Kiefer AG 8304 Wallisellen

Truck loading ramps

Mebag Apparate- und Metallbau 8840 Einsiedeln

Floor screeds

Marrer AG 4658 Däniken

Electrical installations

Elektro Kälin AG 8840 Einsiedeln

Icon

What makes the project special or innovative?

The entire Steinel site stands for modern, sustainable and future-oriented development. Key features include:

  • Ecological wood heating via a district heating network for efficient, resource-saving heat supply
  • Photovoltaic systems on the roofs
  • High-quality, well-thought-out architecture in residential and commercial buildings
  • Synergy between working and living – short distances, shared use, a new identity for the neighborhood
  • Sustainable site development with a clear vision for future generations. These elements give the site its own character and combine quality of life with economic appeal
Icon

How will the infrastructure around the new buildings be improved?

The site benefits from its central location in Einsiedeln and will be further enhanced by the development:

  • Very good public transport connections (train & bus)
  • Convenient access to Zurich, Schwyz and the surrounding regions
  • Optimized routes within the site
  • Harmonious integration into the existing neighborhood
  • A mix of living, working and meeting places

This creates a location that will remain attractive in the long term for residents and businesses alike.

Icon

When can the commercial and residential spaces be occupied?

Commercial building A and residential building D are part of the current construction phase. Move-in dates depend on the construction progress of each building. Commercial building A is being built entirely for Steinel Solutions AG; the move into the new building is planned for September / October 2027. Residential building D will contain 24 rental apartments with 2½ to 4½ rooms. The new apartments are expected to be ready for occupancy in October 2027.

As soon as completion is confirmed, the dates will be announced publicly.

Floor plans, information on availability and rental prices for the apartments will be provided in good time.